835452_c5642f81As you will have heard and seen, there are going to be works to the Greenford Roundabout flyover and that work is going to cause disruption, but what is happening and when is it going to impact on you?

The bearings (pillars) of the Greenford roundabout flyover need to be replaced and whilst the works are due to begin on 31st July and aim to be completed by May 2018,  the main impact will be during the school holidays, as scaffolding needs to be erected must remain in place throughout the duration of the works…

The inner lane of the flyover will be closed throughout 31 July – 12 September

In addition to this, the flyover will be closed in its entirety overnight (22:00-5:00) on the following dates:

26/7/17 – 28/7/17

31/7/17

13/9/17

28/11/17

1/12/17 – 15/12/17

16/12/17 – 13/1/18 (no works from 23/12/17-7/1/18)

16/2/18

4/5/18 – 6/5/18